Construction Status May 2018
Construction Status May 2018
May-2018
 
We’ve got 19 floors completed and Block work done for 5 floors. You’ll be pleased to know that our construction is running on schedule and expected to be complete by the promised date. Visit us today to find out more about Ohana!

Construction Status April 2018
April-2018
 
With 18 floors already looming tall and block work completed for four floors, our construction is running right on schedule. The photos serve testimony to our dedication to using only high-quality construction material! Visit our site today and find our why Ohana is the perfect home for you!

Construction Status January 2018
January-2018
 
The photos serve a testimony to the steady work progress at OHANA. Having finished the construction work of 17 floors and 2nd floor Masonry work; we’re glad to remind you that we’re well ahead of our scheduled date of completion. As a part of the update, we’ve put together this construction report to help you get a better understanding of the pace, of what’s happening at the site.

Construction Status December 2017
December-2017
 
Progress at the OHANA site is coming along promisingly. We are well ahead of our scheduled date of completion and have finished the construction of 15 floors already. In our effort to bring you transparency and convenience, we’ve put together this construction report to help you get an idea of what’s happening at the site. The photo should serve as a simple visual progress indicator.